News - Paks 2 EN
News
The authority issued the implementation license for the new NPP units
26.08.2022
The implementation license is the precondition for the project to enter the construction phase.
József Eck received the Hungarian Gold Cross of Merit
22.08.2022
The Program Director of Paks II. Ltd. received the state award on 22 August.
The European Parliament recognized nuclear energy as a sustainable energy source
07.07.2022
The EU Act recognizing nuclear as a sustainable energy source could enter into force on 1 January 2023.
Péter Szijjártó: the investment enters a new phase
01.07.2022
The Paks investment may enter the second, implementation phase in September, at which time Gergely Jákli will take over the management of Paks II. Ltd.
Paks II. Ltd. received the manufacturing license for the core catchers
30.06.2022
These long lead items will be installed at an early stage of the implementation.
The eighth issue of AtomSphere is published
21.06.2022
The June issue of the Paks II. Ltd.’s company magazine is now available online and in print.
The HAEA has issued the license for the implementation of soil consolidation
11.06.2022
Based on the license, important site preparation activities related to the construction can be started.
Paks II. Ltd. received its cut-off wall construction license
26.05.2022
The recently issued license is a critical milestone for the start of the construction of the new NPP units.
János Süli received his state secretary’s credentials
25.05.2022
The construction of the two new NPP units serves our national security, national economy and national strategy interests.
Péter Szijjártó: Our aim is to speed up the project
19.05.2022
The project of building the two new units is transferred to the Ministry of Foreign Affairs and Trade. The aim is to accelerate the investment in Paks.
New construction licenses were issued by the authority
06.05.2022
New facilities of the Construction and Erection Base have recently received a construction license from the Hungarian Atomic Energy Agency (HAEA).
The construction of Paks II. is of national economic and national security importance
05.05.2022
At the meeting of Péter Szijjártó and Alexey Likhachev, the director general of Rosatom confirmed: his company is able to implement the investment.
The cooperation continues with the Western suppliers
05.04.2022
The Western European and US suppliers of the Paks II. investment declared clearly, they want to continue the cooperation.
Hungary's electricity import dependence is also high by European standards
11.03.2022
In 2021 there was a 30 days worth of time period, when Hungarian electricity consumption was covered by at least 40% of import.
The CEO of Paks II. Ltd. received the Prima Award
10.03.2022
István Lenkei, who was awarded for his outstanding and exemplary performance in his profession, spent his entire career in the nuclear energy sector.
Virtual tour on the new nuclear power plant’s site
03.03.2022
A new tool was added to the communication toolkit of Paks II. Ltd.
There is no secure supply of electricity without the Paks II. investment
01.03.2022
The Paks II. project guarantees the secure electricity supply and the affordable electricity – highlighted János Süli at the event of Századvég.
The investment was the main topic of the Szekszárd Entrepreneurship Forum
21.02.2022
The entrepreneurs from Tolna County were able to get information about the Paks II. project.
Production licensing for the core catcher begins
11.02.2022
The compilation of documentation for another long-lead item has been completed by Paks II. professionals.
A joint year evaluation by Paks Nuclear Power Plant and Paks II. Ltd.
09.02.2022
The full broadcast is also available online.
— 20 Items per Page